on ‎2022 Feb 26 5:16 PM
Hi Experts
BDC program is made to create production order of FG and SFG. FG and SFG have different group counter number as we are using reference operation set. If we execute BDC program for 5 FG and 3 SFG, every time it ask for group for ref operation set "S" and manually it has to entered. This create problem for user.
So is it possible to configure system so that it can take group number for FG and SFG automatically during production order creation?
If yes, then how?
Request clarification before answering.
Hi,
You can control with Selection group in order dependent parameters OPJH