GR qty more than inbound delivery quantity in PRDI EWM

LEXCOE
Discoverer
0 Kudos
186

Inbound delivery got status is red due to the error – GR qty more than inbound delivery quantity. Hence the delivery gets into red status.

Unpacked the products from HU. No HU available now.

Please help us to get the delivery to green at the earliest.

Accepted Solutions (0)

Answers (1)

Answers (1)

Ajit_Routray
Active Contributor
0 Kudos

Hi @LEXCOE,

Please find the root cause, solution to fix the issue and let usknow if issue persists.

"Unpacked the products from HU. No HU available now. ->  Please follow "simply try to increase the quantity to unblock the item or unpack some planned stock, but in some cases it indicates a fake GR link problem, if the related HU is still planned."

 

Extra pack quantity

The quantity of role "GR and Packed, Not GR Posted" is greater than the delivery quantity

 

 

********************************************************************************************

How quantity role PAN "GR and Packed, Not GR Posted" works?

(PAN) GR and Packed, Not GR Posted: This is the sum of GR posted and packed, but not yet GR Posted (aka Planned Packed) stock. Calculation is based on the GR qty role (originally from the GR document flow links) and on the quantities packed in Planned HUs. At the end of putaway process (Putaway Status = Completed), PAN quantity should be EXEC = REQ (if item is 10 EA, then EXEC = 10 EA, OPEN = 0 EA, REQ = 10 EA). Sometimes PAN EXEC will be greater than the REQ as of normal processing (which blocks the item), in this case, simply try to increase the quantity to unblock the item or unpack some planned stock, but in some cases it indicates a fake GR link problem, if the related HU is still planned.

PAN, GR, and PA (pack) quantity roles during processing steps of an Inbound Delivery

GR = sum of GR document flow link quantities
PA = packed stock in Planned HU + planned physical stock
PAN = GR EXEC + packed stock in Planned HU

Color legend for below tables:

  • Red: Changed/recalculated at the current step

Scenario 1: item with 10 EA, to be packed

     Inbound Delivery created,no planned HUs yetInbound Delivery created,stock is packed into planned HU(s)GR posted Putaway Completed
GRGoods ReceiptEXEC001010
GRGoods ReceiptOPEN101000
GRGoods ReceiptREQ10101010
PANGR and Packed, not GR PostedEXEC01010*10
PANGR and Packed, not GR PostedOPEN10000
PANGR and Packed, not GR PostedREQ10101010
PAPackEXEC010100
PAPackOPEN100010
PAPackREQ10101010

* recalculated, but change is not visible, because it is still 10 EA EXEC, but earlier it was the planned stock 10 EA (= 0 EA GR link quantity  + 10 EA planned, packed stock), now it is the GR posted 10 EA (= 10 EA GR link quantity + 0 EA planned packed stock (as the stock is now "physical")).

Scenario 2: item with 10 EA, packed into 2 HUs

     Inbound Delivery created,no planned HUs yet1st plannedHU createdGR posted forfirst HU2nd plannedHU createdGR posted for2nd HUPutaway Completed forthe 1st HUPutaway completed forthe 2nd HU
GRGoods ReceiptEXEC0044101010
GRGoods ReceiptOPEN101066000
GRGoods ReceiptREQ10101010101010
PANGR and Packed, not GR PostedEXEC044*1010*1010
PANGR and Packed, not GR PostedOPEN10660000
PANGR and Packed, not GR PostedREQ10101010101010
PAPackEXEC044101060
PAPackOPEN106600410
PAPackREQ10101010101010

Scenario 3: item wtih 10 EA, packed into 2 HUs, but putaway posted for the 1st HU before receiving the 2nd HU

     Inbound Delivery created,no planned HUs yet1st plannedHU createdGR posted forfirst HUPutaway Completed forthe 1st HU2nd plannedHU createdGR posted for2nd HUPutaway completed forthe 2nd HU
GRGoods ReceiptEXEC004441010
GRGoods ReceiptOPEN101066600
GRGoods ReceiptREQ10101010101010
PANGR and Packed, not GR PostedEXEC044*41010*10
PANGR and Packed, not GR PostedOPEN10666000
PANGR and Packed, not GR PostedREQ10101010101010
PAPackEXEC0440**660
PAPackOPEN1066104410
PAPackREQ10101010101010

** Pack quantity role is 0 EA at this point, because after first HU putaway is completed, there are no longer planned or physical packed stock on this item.

Scenario 4: fake GR link on item 10, which is packed into planned HU. Planned HU was not received, it is still showing as planned on HU tab

     Item is packedinto planned HUfake GR link created,item blockedAfter removingfake GR link
GRGoods ReceiptEXEC0100
GRGoods ReceiptOPEN10010
GRGoods ReceiptREQ101010
PANGR and Packed, not GR PostedEXEC1020***10
PANGR and Packed, not GR PostedOPEN000
PANGR and Packed, not GR PostedREQ101010
PAPackEXEC101010
PAPackOPEN000
PAPackREQ101010

*** this is the sum of the GR link quantities and the still planned stock quantity (10 EA + 10 EA), which is obviously greater than the item quantity (10 EA).

Source: https://help.sap.com/docs/SUPPORT_CONTENT/sewm/4248188860.html

Kind Regards,

Ajit