on 2016 May 06 12:21 PM
Hi Experts We are facing an issue with the GR processing Time, where it is considering Weekends(Sat/sun) for GR time calculation, while Sat/Sun are actually non-working in the Calendar assigned. We assigned Calendar resource as the Inbound Handling Resource. I also can see the resource capacity is also showing Sat/Sun as non-working. Resource is assigned to Model. Not sure what causing this behaviour? Thanks Rishi
Request clarification before answering.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.