Hi All,
For some reason the validity dates inside the product substitution procedure are not considered during the creation of sales order.
M1 M2 01-oct-2015 20-oct-2015
When I create a sales order for 26-oct-2015, I can see the product substitution is getting kicked in for M1 and system is doing the avail check for M2 as well.
Please advice.
Thanks,
Suhail Shaik
Request clarification before answering.
Hello Suhail -
What is the APO release you're using ?
As of SCM 7.0 EHP3, MBDAT of the order is considered to validate the Substitution rule. Check if your MBDAT is falling in the validity.
Thanks & Best Regards,
Babu Kilari
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Babu - thanks for your reply, yes I am aware of the MAD and it is same as the delivery date.
SAP provided me a note and the actual check seems to be working fine now however in the APO overview screen I still see M1 and M2 when the dates are not valid and I have posted the same back to SAP.
I will update once I get this answered.
Thanks,
Suhail Shaik
| User | Count |
|---|---|
| 15 | |
| 5 | |
| 5 | |
| 3 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.