on 2018 Jun 06 10:54 AM
Hello ,
Wanted to setup a scenario where goods are transported from A -> C via hub B.The use of hub B is just for driver team swap and no unloading of goods is required.We had created a default route A->B->C and its activated at Freight unit building rule level.B is setup as a transhipment loc to A and C .
When the forwarding order is created default route is applied and 2 stages are created A->B and B->C.The same stages are transfered to FUs as well.
Now when the FUs are getting optimizer planned its creating 2 Freight orders , one from A->B and the other B->C. Is it a normal behaviour?We wanted to create a single FOR with multiple stages and do the internal settlement as its being executed by own resource.
Kindly advice on how the creation of stage wise FOR s can be prevented.
thanks
Request clarification before answering.
| User | Count |
|---|---|
| 6 | |
| 5 | |
| 3 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.