Forecast was existing for product from this week onward - in both DP and SNP. I deleted forecast using RLCDELETE and released it from DP to SNP using MC90 (using dates from current date to future date). I see FC got released into SNP but not for current week but from 10th of December onward. In DP planning book I can still see forecast values for this week and next week. What could have caused forecast not to release for near future?
Request clarification before answering.
Hello,
In /SAPAPO/MC90 please check the release horizon ('From date' - 'To date') what is Planning Buckets Profile used.
Do you have used /SAPAPO/SDP_SPLIT a period split profile ?
Also check the location has a shipping calendar which uses a factory calendar with non-working days.
Check badi /SAPAPO/SDP_RELDATA method CHANGE_RELDATA is active in system
The actual availability of the forecast order can be seen in forecast tab of /SAPAPO/RRP3. shows that the forecast creation (release) start date and end date. So check the forecast detail tab for checking the span of forecast requirements.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 18 | |
| 16 | |
| 5 | |
| 3 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.