Forecast release date not current

0 Likes
538

Forecast was existing for product from this week onward - in both DP and SNP. I deleted forecast using RLCDELETE and released it from DP to SNP using MC90 (using dates from current date to future date). I see FC got released into SNP but not for current week but from 10th of December onward. In DP planning book I can still see forecast values for this week and next week. What could have caused forecast not to release for near future?

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar
Active Contributor
0 Likes

Hello,

In /SAPAPO/MC90 please check the release horizon ('From date' - 'To date') what is Planning Buckets Profile used.

Do you have used /SAPAPO/SDP_SPLIT a period split profile ?

Also check the location has a shipping calendar which uses a factory calendar with non-working days.

Check badi /SAPAPO/SDP_RELDATA method CHANGE_RELDATA is active in system

The actual availability of the forecast order can be seen in forecast tab of /SAPAPO/RRP3. shows that the forecast creation (release) start date and end date. So check the forecast detail tab for checking the span of forecast requirements.

Best Regards,

R.Brahmankar

0 Likes

Thanks; got it.