cancel
Showing results for 
Search instead for 
Did you mean: 
Read only

Fixed pegging in GATP

Former Member
0 Likes
570

Hi Experts,

    We are using SCM7.0. In GATP, we would like to use the result from planning run, so CTM planning run will create supplys and fixed pegged to demand. During GATP check, we would like to use the pegged supply to do check.

     In scope of check, we have already configured as 'consider both manual and automatic fixed pegging'.

     In below example, the sales order is fixed pegged to a deployment orders which is available on 2/27. But during GATP check, this sales order is still using the earlier PR (which is available on 2/16) to confirm and schedule. My expectation is the sales order should use the fixed pegged deployment orders as the supply and ATP check based on that. Is this how fixed pegging supposed to work? What do I miss here?

    

thanks,

Wenyan

Accepted Solutions (1)

Accepted Solutions (1)

Abhishek_Kunchala
Active Participant
0 Likes

Hello Wen,

In the check instructions that you use, did you maintain that the product check should take place on the Fixed Pegging Relationships?

Regards

AK

Former Member
0 Likes

Thanks AK. I tried that and it worked.

Answers (0)