on ‎2021 Oct 22 12:50 AM
Dear Experts,
There is a question regarding the posting change process in EWM.
Material 1 is converted to Material 2.
The process is initiated from ERP and a PCN delivery gets replicated to EWM and a WT is created in /SCWM/IM_PC.
The destination storage bin determined in the warehouse task is based on the putaway search sequence corresponding to material 1 and not material 2.
Is this standard system behavior ?
Kindly suggest.
Thanks,
Mageshwaran Sivasamy
Request clarification before answering.
Hi Mageshwaran maybe it depends on your warehouse process type customizing? In the section for posting change.
BR,
Daniil