Hi experts

We want to schedule a background job for various nodes of ewm monitor

But not able to find the particular program of each node

Can any one help how to do that

Accepted Solutions (0)

Answers (1)

Answers (1)

JuergenPitz
Product and Topic Expert
Product and Topic Expert

Hi,

first question would be... WHY do you want to do that?

Anyway: the "correct" way for that is to a right mouse-click on the node and select "Process in Background (Spool)" (or something similar). Then you can enter the background scheduling details.

Brgds

Juergen

---

All the above is no official SAP statement.

Want to learn EWM?

Check for EWM courses: https://training.sap.com/trainingpath/Applications-Extended+Warehouse+Management-EWM+in+S4HANA

Get a SAP Learning Hub Subscription: https://training.sap.com/learninghub

And it is EWM. NOT eWM - Duh!

And if your question includes the word "transfer order" - do NOT tag the question with Extended Warehouse Management!

Daniil
Active Contributor
0 Likes

and after you can check SM37 to see the report name ( I guess /SCWM/R_WME_MON_NODE_BTC_RUN )

0 Likes

Hi

I will this try. Our client wants the report of Outbound. Thrice a day. They don't want to run the monitor manually. They want the report automatically

JuergenPitz
Product and Topic Expert
Product and Topic Expert
0 Likes

Hi,

ok. But what does the customer want to see? For scheduling this in any way usefully, you need selection parameters. What outbound delivery orders do they want to see?

Brgds