on 2022 Jan 21 3:06 PM
Hello Experts,
I am performing Material Staging in KANBAN using delivery based strategy(0007).
I have maintained PSA,KANBAN CC,delivery and item types mapping,Partner for delivery.
But when I empty the KANBAN i get the below error message.
The same works fine for WT based strategy(0009)
Can anybody please let me know what could be wrong?

Thanks,
Rakesh.
Request clarification before answering.
I will suggest you to check the control cycle availability for this material and PSASTAGE data correctly setup. If the master data is there, I will suggest to check the delivery definition in EWM integration if it is decentralised EWM with ECC.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Yaping,
The CC and PSA STAGE is correctly maintained and this is embedded environment.
I was able create Outbound delivery in ECC for stock reversal 562.
The delivery took shipping point,ship to party details from the customization.
But this is not happening in KANBAN case and is unable to find some data.
I did a basic debugging and found that it is unable to fetch Ship to party and Shipping point data.
But these data are getting picked for stock reversal scenario.
Thanks,
Rakesh.
Hi Rakesh,
Based on your debugging data, it seems you miss some configuration for WHS internal delivery parameter setup if it is decentralised EWM system. You can check the configuration for default internal goods issue/receipt setup here:
ECC - Logistics Execution - Decentralised WMS integration - Central Processing - Application - Define Interface to... - Delivery-relevant data for Warehouse Number.
You can setup default shipping point, ship to party, vendor data here for any WHS internal deliveries.
Cheers
| User | Count |
|---|---|
| 6 | |
| 5 | |
| 3 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.