Hi Gurus
Our system landscape ECC 5.0 and SCM5.1,
we created project order and attached component and triggering ATP and generate the planned order in
APO, Network transfer to APO
We are getting Error queue "/sapapo/cif_prj_inbound
and Invalid I / O node configuration
we have implemented the SAP Note : 1114989 for the same error
still we are facing the same issue. please help me
Thanks and regards
dhaivakumar
Request clarification before answering.
Hi Dhaivakumar,
Check sap notes 828917 & 823418
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Dhaivakumar,
Have you solve your issue ?
We have the same problem today so your help will be grateful..
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I think the problem may be in the way the component is placed in the order. How are you adding the component? Does this component/location exist in APO? Is the schedule line or item number being assigned to the component - without either one of these you will get an i/o error.
Andy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
5 | |
4 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.