Does optimizer respects freeze horizon?

445

Hello Experts,

We have a 4 week frozen horizon during our supply planning. when running optimizer i could see that freeze horizons are not respected. the demands in freeze horizon does not gets fulfilled and also does not get rolled over to 5th period as it does for heuristic . is this the standard behavior of optimizer or we are missing any settings wrt freeze horizon.

Thanks for your time and advice.

Regards,

Hari

Accepted Solutions (1)

Accepted Solutions (1)

former_member654033
Contributor
0 Kudos

Hi Hari,

Please read SAP Help for frozen Horizon behavior (Its different than APO Behavior)

https://help.sap.com/viewer/feae3cea3cc549aaa9d9de7d363a83e6/2005/en-US/d5327c68776a4ef785ae4f595f54...

Regarding Carry forward, you have to model Max delay and Late delivery costs.

Thanks

Girish

Answers (1)

Answers (1)

neeraj_deshkar1
Active Participant

Hello Hari,

Optimiser does respect frozen horizon. However you have to use Minimum Production Receipts of along with specifying frozen horizon in location product MDT.

Regarding demand carry forward - You need to use late delivery periods & cost rate.

Hope this helps.

Thanks,

Neeraj