on 2015 Mar 04 3:26 PM
Hi,
We have scenario where planning Gap is required for few months during the entire horizon for respective group of products.
e.g.
Say horizon is 1 year ( Jan to Dec. )
product A - > gap needed for July,Aug & Sep. ( i.e. System can plan Jan to June and Oct-Dec but it should not plan anything during July to Sep)
Product B-> gap is June,July ( i.e. System can plan Jan to May and Aug-Dec but it should not plan anything during June and July )
Note:- we can receive Sales order as per customer order but will not plan and supply during these GAP period.
We thought of using Transportation Lane validity
e,g, for product A create two Lanes with different validity date.
TLane1 :- validity from 01-01-2015 till 30-June2015
Tlane 2:- Validity from 01-10-2015 till 31-12-2015
but SNP Heuristic is not respecting this ( it seems there is some flaw , might need to check sap note)
Please suggest
Thanks
Samir
Request clarification before answering.
Hi,
Try using planning calendars. It is assigned in MAT1 (Lot size view).
You will need to define two different planning calendars, one for each material.
Kind Regards,
Mariano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Samir,
You can create the calendar in APO in t-code: /SAPAPO/CALENDAR
Then this can be assigned in the planning calendar field in MAT1 (Lot Size view).
You can find a step by step guide here:
Kind Regards,
Mariano