Do not want system to plan anything during gap period

samir_ali
Participant
0 Kudos
128

Hi,

We have scenario where planning Gap is required for few months during the entire horizon for respective group of products.

e.g.

Say horizon is 1 year ( Jan to Dec. )

product A - > gap needed for July,Aug & Sep.  ( i.e. System can plan Jan to June and Oct-Dec but it should not plan anything during July to Sep)

Product B-> gap is June,July ( i.e. System can plan Jan to May and Aug-Dec but it should not plan anything during June and July )

Note:- we can receive Sales order as per customer order but will not plan and supply during these GAP period.

We thought of using Transportation Lane validity

e,g, for product A create two Lanes with different validity date.

TLane1 :- validity from 01-01-2015 till 30-June2015

Tlane 2:- Validity from 01-10-2015 till 31-12-2015

but SNP Heuristic is not respecting this ( it seems there is some flaw , might need to check sap note)

Please suggest

Thanks

Samir

Accepted Solutions (0)

Answers (1)

Answers (1)

MarianoCabalen
Active Contributor
0 Kudos

Hi,

Try using planning calendars. It is assigned in MAT1 (Lot size view).

You will need to define two different planning calendars, one for each material.

Kind Regards,

Mariano

samir_ali
Participant
0 Kudos

Thanks Mariano,

Can you please give more details on the calendar.

1) what about production calendar assigned in Location master. 

2) Can you tell me steps to create new calendar with gap of 3 months ( for July,Aug & Sep)


Thanks

Samir

MarianoCabalen
Active Contributor
0 Kudos

Hi Samir,

You can create the calendar in APO in t-code: /SAPAPO/CALENDAR

Then this can be assigned in the planning calendar field in MAT1 (Lot Size view).

You can find a step by step guide here:

SAP SCM APO SNC: Maintain Planning Calendar (Time Stream)</title><link type='text/css' rel=...

Kind Regards,

Mariano