Dears,


(Besides T-Lane) Why and when would the standard key figure distribution receipts planned (at the destination location) have no supply location ?

Secondly why would manually changing this key figure in the data view (standard SNP data view) AT the destination location does not overwrite the existing value but instead ADD's up. This is in entire horizon. (though SNP stock transfer horizon is 0).

Likewise Deletion and attempting to save, reverts it back to original number. UNLESS I go select the order and delete.. by double clicking the cell. in which case are planned distribution receipts get fixed across the horizon.

Thanks

Amit


Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Likes

Thanks Rupesh,

Isnt this the same as what I see by double clicking on the cell in data view ?

rupesh_brahmankar
Active Contributor
0 Likes

Hello,

Yes right, please share the screen shot of RRP3 and SDP94 too of same order.

Best Regards,

R.Brahmankar

Former Member
0 Likes

What is meant by 'assignment' of source of supply source? Isn't the program supposed to pick it up from tlane/pds/quotas/prios/costs whatever qualifies? I have tlane valid in this case as shown in the screenshots.

rupesh_brahmankar
Active Contributor
0 Likes

Hello,

Please go to product view /SAPAPO/RRP3 double click in on your order and verify that you have

Source Location and Supply Source.

Best Regards,

R.Brahmankar

rupesh_brahmankar
Active Contributor
0 Likes

Hello,

If the SNP distribution receipts is created without source of supply then it will have no no supply location. I think your both the questions are related to source of supply. Please cross check you have valid transposition lane between to locations and it is assigned to your orders.

Best Regards,

R.Brahmankar

Former Member
0 Likes

Thanks Rupes

T-lane exists and valid. Hence the question. There is only one T-Lane. No quotas, No prios. No this. No that. So simplest possible case. Hence the question.

rupesh_brahmankar
Active Contributor
0 Likes

Hello,

Does your order have the source of supply assignment? If possible share T lane and planning book screen shots.

Best Regards,

R.Brahmankar