on 2023 Feb 01 1:43 PM
Hi All,
Some days back we got a situation where one alternative resource is being used in PV but in APO while checking PDS we saw 3 alternative resources are there. We did re transfer of PV in APO and issue got solved. But user wants to know the root cause why it happened. We saw there are no recent changes made (like addition of extra two alternative resource in ECC). Can anyone help me on this? Currently we are having the same data in quality.
PV is using only one Alternative Resource
PDS Alternative Resource
Request clarification before answering.
Hi Sumanta,
In ECC, there might be three additional resources earlier and that particular PV is transferred to APO. As a result, there were three resources showing in APO.
Now In ECC, they have changed to one resource, because of which after CIFing it is rectified now.
Could you plz check that one.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
5 | |
2 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.