hi,

Currently IBP project inventory calculation:

Current WK= Stock On Hand+ Receipt-Supply

Any other further WK= previous project +Receipt-Supply

If i want to have different calculation, take "Receipt" out of calculation, how can i do it.

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

former_member242371
Contributor
0 Likes

Hi Rex,

You can create a custom key figure with calculation Projected Inventory - Total Receipt.

Thanks,

Rohit

0 Likes

Hi Rohit,

how do i put the formula to capture the previous project stock value into this week for the calculation in the new KF?

Thanks.

Rex

former_member242371
Contributor
0 Likes

Hi Rex,

You can use attribute transformation for time period offset.

Check detail in SAP help link

Thanks,

Rohit