on ‎2018 Aug 07 3:21 AM
hi,
Currently IBP project inventory calculation:
Current WK= Stock On Hand+ Receipt-Supply
Any other further WK= previous project +Receipt-Supply
If i want to have different calculation, take "Receipt" out of calculation, how can i do it.
Thanks
Request clarification before answering.
Hi Rex,
You can create a custom key figure with calculation Projected Inventory - Total Receipt.
Thanks,
Rohit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rex,
You can use attribute transformation for time period offset.
Check detail in SAP help link
Thanks,
Rohit