Hello SAP experts,
We are currently implementing ePPDS DSC edition in order to perform our Detailed scheduling.
One of our business requirements is also to take into account the availability of critical tools ( as a constraint ) required for some operations ( specific machines ) in the planning. It means business should be able to see the clear situations when a machine has available capacity but the tool does not have available capacity or vice versa. The goal is to have visibility of critical tools capacity at the time of planning i.e. before Order processing, this would help in decision making of whether to adopt the plan or revise it. These critical tools are mapped in SAP by a PM equipment.Request clarification before answering.
Hello All,
Sorry for late update of the thread.
This is how we achieved the scheduling based on availability of critical tools:
1st option : The tool is always required for a specific workcenter ( machine )
Using a secondary capacity ( PRT ) as a pooled capacity ( if there are several tools ) on this specific workcenter.
2nd option: The tool is required for workcenter ( machine ) but dependent on the material
Using a sub-operation and a workcenter ( cat type PRT ) with a pooled capacity ( if there are several ) representing so called tool.
Operation 0010: machine where tool is required for specific material
Sub-operation 0010: with workcenter PRT.
Now some particularities apply to sub-operation in PP/DS so you need to be careful when scheduling.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 12 | |
| 7 | |
| 4 | |
| 3 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.