on 2023 Jun 19 4:07 PM
Dear Experts,
Please advise. We see that deployment run deleting the heuristic STR even partial STR created.
Example:
We have heuristic STR of 1000
Stock 250
When I run deployment, confirmed deployment STR created for 250 and we do not see any details unconfirmed STR of 750.
We expect to see conformed STR of 250 and unconfirmed STR of 750.
Please advise.
Thanks & Regards
AB
Assuming your question relates to using SAP APO SNP (not SAP IPB R&S) then this behaviour is part of the SNP deployment heuristics setting (/SAPAPO/RMSDPDEP). You can chose if you want to "delete" the SNP STR independent if you have enough ATD qty at the time of running the deployment -or- if you want to "reduce" the SNP STR by the qty which turned into a DeployedSTR. In your case I assume the "delete" option is used therefore all STRs are deleted although the ATD qty was insufficient.
Regards
Thomas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
6 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.