Deployment optimizer is not considering conrel elements of future start date

sumaghosh
Participant
0 Likes
343

Hi Experts,

We have Deployment optimizer running every day to generate plans for stock transfers from plants to depots based on depot demand.

We noticed that even if STOs ( COnrel) elements are available system is deploying the unrestricted stocks without the STO quantity subtracted from it.

This is causing huge issue of STO qty > Available unrestricted stock.

Can someone throw some light , how to consider all the STOs as ATI elements irrespective of date.

Thanks.

Accepted Solutions (0)

Answers (2)

Answers (2)

sumaghosh
Participant
0 Likes

The issue was resolved by increasing the SNP checking horizon to 5 from 1.

sumaghosh
Participant
0 Likes

Hi rupesh.brahmankar3,

Yes they are within the demand horizon.

rupesh_brahmankar
Active Contributor
0 Likes

Hello,

Did you check the optimizer log?

Where you can analysis which supply elements and dates are considered in deployment run

Best Regards,

R.Brahmankar