Hi All,

I have a question regarding LifeCycle Management and Demand Planning.

Follow situation I have in my system. I have a product group with two materials. Material 2 should be replace material1. For that reason, I create a phase out, phase in and a like profile. Furthermore I greate the necessary profiles for statistical forecast.

So far so good. The history (after a realignment) is for both products 9.000 pc.

If I now load material 1 into the planning book and start the univariate FC with the lifecycle profils, the system start not the phase out phase with 9000,the system start with 18.000. This is the sum of the product group. I check this with furhter values and I can say. that the system not use the figure on material level, it use the figure on product group level.

Can you help and say, what I have to do, that the system is working on the right level ?

Thanks in advance

Oliver

Accepted Solutions (1)

Accepted Solutions (1)

OliverA41
Active Participant
0 Likes

I have solved this and it was a mistake in a fc Profile