on 2025 Apr 11 8:39 AM - last edited 4 weeks ago
Hi Experts,
I would like to ask: for a customer who has newly implemented SAP and wants to use the DDRMRP , is it possible to directly maintain historical daily consumption data? I tried to maintain the consumption data in the Forecasting view of the material master, but when I run the schedule production classification, the system still notifies me that there is no consumption data , Is it necessary to have actual delivery records before DDRMRP can be used?
Best regards
Lance
Request clarification before answering.
Hi @lannew
Did you maintain the following transactional data:
Goods Issue data for ADU calculation and/or
Planned Independent Requirement for ADU calculation
Maybe you also check customizing one more time for:
Buffer Profile
ADU Exclude Movement types
I assume the transactional data is the issue, but let me know if it works.
Best regards, Markus
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
3 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.