Hi, I am trying to understand how the below dates can be auto-populated. At the moment, I am using the condition for PU/DLV window determination in the FU type config to drive the dates. I was able to get the dates under Destination populated correctly using the values in the condition table shown below. However, I don't seem to be able to do the same with those dates for the source. Note that I have tried with populating values in the condition table for earliest stay, premature stay, delayed stay and latest stay for the TO Stop Category 'O'. Did I misunderstand the use of those fields? Appreciate any pointers to have the dates under Source populated.

Destination

Start Date (Requested) = Delivery Date

End Date (Requested) = Delivery Date + Delayed Stay (from condition table)

End Date (Acceptable) = Delivery Date + Latest Stay (from condition table)

SFC_0-1743481032688.png

Example of the condition table:

SFC_1-1743481128267.png

Cheers

SFC

 

Accepted Solutions (1)

Accepted Solutions (1)

Ajit_Routray
Active Contributor

Hi @SFC3 

"Did I misunderstand the use of those fields? Appreciate any pointers to have the dates under Source populated."

For outbound Delivery/ Customer Order/Sales Order - O Means Source means Shipping Point and I means Customer means Destination... Please see example below with data of Freight Unit created from Sales Order, influenced to change date and let us know if any questions.

Screenshot 2025-04-01 at 3.20.56 PM.pngScreenshot 2025-04-01 at 3.16.27 PM.pngScreenshot 2025-04-01 at 4.18.44 PM.png

For inbound delivery, it would be reverse

Details link:

 https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/e3dc5400c1cc41d1bc0ae0e7fd9aa5a2/beb00cb0f7ae427a953...

https://userapps.support.sap.com/sap/support/knowledge/en/2486759

https://community.sap.com/t5/supply-chain-management-blogs-by-sap/flexible-pickup-delivery-window-in...

Kind Regards,

Ajit

SFC3
Participant
0 Likes
Hi Ajit, thanks for the references. I have done further testings and it seems that my issue is with the type of constraints I assigned. If I use '3', the dates are all calculated.