Day level in Time Series

Former Member
0 Likes
794

Is there a way to run Time Series Optimizer in a day level ?

How ?

Accepted Solutions (1)

Accepted Solutions (1)

neeraj_deshkar1
Active Participant
0 Likes

Hi Angel,

Please check if you can see keyfigure data via planning objects. If yes, then I suspect an issue with UoM conversion. Then you would need to purge & reload all UoM conversions.

Else please check whether UoM conversion MDT is maintained. Final option would be to purge & reload all data since roots are changed.

Regards,

Neeraj

Answers (4)

Answers (4)

mkorndoerfer
Product and Topic Expert
Product and Topic Expert
0 Likes

Hi Angel,

Please make sure that all Input, Output, Input/Output, and Indirect Input Supply Key Figures (except Aggregated Constraints) are at Daily level. If at least one Supply KF is not at Daily level, it shouldn't work.

Best regards,
Matheus

ankpatel
Contributor
0 Likes

Hi Angel,

Did you reload all the data after changing root Planning levels? If not, that has to be done as you have changed the existing root planning levels. If you have already loaded the data, check in Master data Planning Object if you can see any data or not.

Ideally, if you have loaded the data after changing PL, you should be able to see the data.

Regards

Ankur

neeraj_deshkar1
Active Participant
0 Likes

Hi Angel,

Yes, it's possible.

You would need to change roots of all planning levels to DAY from Technical Week or create new planning levels with Day as root & assign all keyfigures to these planning levels.

Regards,

Neeraj

Former Member
0 Likes

Thank you Neeraj,

I've already changed all those planning levels, but now i can't see data from my planning views in excel, it's like not having master data. Do you know why ?

If i make a change in the template, (from weeks to days) this message comes up.

ankpatel
Contributor
0 Likes

Hi Angel,

Yes, you can run Timer Series Optimizer at the day level but you have to change all the direct and indirect input KF for Supply to the root level of Day.

Regards

Ankur

Former Member
0 Likes

Thank you Ankur,

I've already changed all those planning levels, but now i can't see data from my planning views in excel, it's like not having master data. Do you know why ?

If i make a change in the template, (from weeks to days) this message comes up and still showing weeks, not days.