Data Integration is not generating time periods for the custom time profile

srikant9099
Explorer
0 Likes
1,132

Hello Experts,

I created a custom time profile(W, M, Q, Y) for the period 2020 to 2030) and use Data Integration with Prefill Template -> With New Time Periods. But it's not generating any time periods.

Please advise.

Thanks

Srikant

Accepted Solutions (1)

Accepted Solutions (1)

piyush_parekh
Active Contributor
0 Likes

Hi Srikant,

System cannot aggregate data from default calendar week to month. Pls change Period Type of time level Week to Technical Week. Activate time profile and then download time profile with pre-fill template.

If you don't want to use technical week as period type, create your own time profile data file and then upload it.

Hope this helps!!

Regards,

Piyush

srikant9099
Explorer
0 Likes

Hi Piyush,

Thanks for the response.

Yes. I don't want Tech.Week as period type.

Please help me in creating the custom time profile with W, M, Q, Y period types. Please share a sample file for my understanding.

Appreciate your help on this.

Thanks

Srikant

Answers (2)

Answers (2)

former_member654033
Contributor

Hi Srikant,

What you are trying to do is not possible because in time profile calendar week cannot be mapped to calendar month without technical week concept.

Only way to create such type of time profile is following 4-4-5 type of calendar, hence it will become manual creation of time profile where calendar week will map to custom month.

  1. Week
  2. Custom Month Definition (Standard month is not possible)
  3. Quarter
  4. year

Thanks

Girish

srikant9099
Explorer
0 Likes

Hi Girish,

Thanks for your response.

Yes, I want to create a custom time profile with the period type (W, M(Custom), Q, Y). I tried to create the custom time profile but getting the below errors:

Missing PERIODID for PARENTID .

Period was rejected due to other inconsistent periods.

I am struggling to understand PARENTID and PERIODID mapping. And how to generate the periodid for the time profile.

It would be great if you share a sample time profile.

Appreciate your help on this.

Thanks

Srikant

former_member654033
Contributor
0 Likes

Hi

Download time profile from SAPIBP1, UNIPA or SAP RDS (I cannot attach .csv file here)

- Remove Day periods (TP Level = 1)

- Remove TW Periods (TP Level = 2)

- Calendar Week definition will remains same

- Modify Month definition (so it always ends of sunday, end of calendar week)

- Modify Quarter Definition (So it always ends on Sunday when month ends, End of Month 3,6,9,12)

- Modiify year Definition (So it always ends on Sunday when quarter ends, End of Q4)

Then try uploading

Thanks

Girish

srikant9099
Explorer
0 Likes

Hi Girish,

Thanks for the response. Let me try this and get back to you.

Regards,

Srikant

lokesh_reddy4
Active Participant
0 Likes

Hi Srikant,

Run below job.

"Create Time Periods for Time Profiles"

Thanks and Regards,

Lokesh Reddy

srikant9099
Explorer
0 Likes

Hello Lokesh,

Thanks for the response.

As advised, I ran the "Create Time Periods for Time Profiles" job. I am getting the below error.

"Period types of time profile level 1 and 2 are not compatible"

Here is my time profile setting.

Please advise.

Thanks,

Srikant