Cumulation of capacity

Former Member
0 Likes
614

Hello,

I have to start using Capacity planning in my factory. But the workcenter capacity have been setting without considering real capacity. Despite that, I can't change the capacity configuration because it would change the scheduling.

I thought I could use "fake" workcenter with the accurate capacity, linked them to the real workcenter that receive the demand throught a hierarchy. with the cumlation of requirement capacity, it,s working.

But now, they are asking me to create bigger hierarchy, representing a section of the factory. I consider creating a hierarchy of 3 levels ( level 1 : root, level 2 : fake workcenter, level 3 : Workcenter with requirement capacity). Is is possible to cumulate capacity requirement from level 3, but the available capacity from level 2 ?

Thanks

View Entire Topic
Abhishek_Kunchala
Active Participant
0 Likes

Hello Marine,

SAP standard functionality allows resource hierarchy calculation only for 2 levels. The following links might be helpful to you.

https://archive.sap.com/discussions/thread/3856519

https://archive.sap.com/discussions/thread/3823242

Regards

AK