Hi guys,

i am creating new Materials/ SKU's for production side of plant and have come across an issue my IT team cannot find a solution for.

We cannot get the process order to print out a preparation sheet nor a mixing sheet.

i have completed ZMIX, C202 and MM02 and i have checked them against our DATA for input errors.

i have made multiple new materials and have had no issue like this yet.

i have checked MRP controller is correct.

i have checked Bill Of Materials is correcti have checked sort strings are correct.

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar
Active Contributor
0 Likes

Hello,

ZMIX is not a standard SAP transaction. So it is difficult for community members and experts to answer your query.

Better to check this with your IT technical team.

Best Regards,

R.Brahmankar

0 Likes

I have and they are stumped.

Thinking we may need to just create a new master recipe as we have been at it for a couple days now and just cannot find issue with it.

rupesh_brahmankar
Active Contributor
0 Likes

Hello,

May be debuging can help here. If new master recipe is working fine then better you should compare old and new master recipe.

Best Regards,

R.Brahmankar