a month ago
Hi,
I would like to create deliveries with future stock. The process is as below
1) sales order is created for FERT materials. As stock is not available, schedule lines are not confirmed.
2) with MRP run, PR is created.
3) PO is created from PR.
4) BOP job is executed.
5) with BOP run, schedule line is confirmed with future stock.
I would like to create delivery a few days in advance, so that warehouse folks can plan the logistics activities. However, when I tried creating delivery, I was getting error "Only 0 ST of material XXXXX available".
Also, when i was checking SAP help, I saw below:
*********************************************************************************************
Request clarification before answering.
Hi,
I assume ATP is active in your item category, correct? Please check it in transaction 0VLP.
Also, make sure the AvailCkOff field is left blank.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.