Create delivery with future stock

KC18
Explorer
0 Kudos
131

Hi,

I would like to create deliveries with future stock. The process is as below

1) sales order is created for FERT materials. As stock is not available, schedule lines are not confirmed.

2) with MRP run, PR is created.

3) PO is created from PR.

4) BOP job is executed.

5) with BOP run, schedule line is confirmed with future stock.

I would like to create delivery a few days in advance, so that warehouse folks can plan the logistics activities. However, when I tried creating delivery, I was getting error "Only 0 ST of material XXXXX available".

Also, when i was checking SAP help, I saw below:

*********************************************************************************************

Configuration for Deliveries

For all options of the Availability Check field (except the No PAC Check option), the product availability check for a delivery only considers stock and deliveries. The No PAC Check option confirms all requirements for the requested delivery date, as for sales orders.
*********************************************************************************************
Does this mean, we can't create deliveries with future stock?
 
Thanks in advance!

Accepted Solutions (0)

Answers (1)

Answers (1)

RAHEEL_BABAR
Active Contributor
0 Kudos

Hi,

I assume ATP is active in your item category, correct? Please check it in transaction 0VLP.

Also, make sure the AvailCkOff field is left blank.

Regards

KC18
Explorer
0 Kudos
Hi Raheel,