on 2023 Jan 19 1:21 PM
Hello Experts,
I am new to the IBP order-based planning. Can someone please explain how to create a customer source of supply in the OBP?
Please advise.
Thanks
Srikant
Request clarification before answering.
Hello Srikanta,
OBP Plans at a Material Location Level with sales order confirmations happening by Customer. Sales Orders are visible in OBP by 'Material Availability Requirement Date' and not by 'Requested Delivery Date'.
Because OBP Doesn't plan for demand by Customers ( in contrast to Time Series Planning), it doesn't have MD for Customers source of supply where you can enter lead time for customers for plan accordingly.
Thanks
Gaurav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi srikant90,
are you modeled Flexible or External master data for OBP?
Best Regards,
Lingaiah
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.