Cost rates by location-product in IBP R&S Order-Based

Former Member
0 Likes
783

Hi Experts,

We have the following business case: for an execution of Constrained Forecast Run Using Optimizer, we want to model a different Late-Delivery Cost Rate by location-product combination, ie, example, for a product A, apply a higher cost rate to location L1 than location L2.

How is possible model this case in R&S order-based.

Best regards,

Accepted Solutions (1)

Accepted Solutions (1)

MichaelMack
Product and Topic Expert
Product and Topic Expert

Hi Dagoberto,

unfortunately with current IBP rel. 1808 it is no possible to maintain late delivery cost by Loc-Prod directly.

The Late-Delivery Cost is pre-calculated for the Optimizer using Global Late-Delivery Cost Rate (Job Parameter) and the Segment of the rule.

option to model your requirement is to create a demand prio rule with following 2 segments:

- segment 1 = condition: all demands at Location L1

- segment 2 = condition: all demands at Location L2

Optimizer will then prioritize demands at Location L1 higher than L2.

A direct maintenance of late delivery cost rate at Loc-Prod level is on the Roadmap and currently planned for 1905 release.

thanks and regards

Michael

Answers (1)

Answers (1)

Irmi_Kuntze
Product and Topic Expert
Product and Topic Expert

As far as I know, you need to wait for the next release 1811, because cost rates on material-location level should be coming with it

Should be available in around 2 weeks or later, depending on your upgrade plan

Check the what's new section in 1811 for it

Yours

Irmi