Convert A Purchase Requisition (AG) to Planned Order (AI)

Former Member
0 Kudos
694

Dears,

I have a purchase requisition with a source of supply (external vendor loc type 1011) in APO and also in ECC.

I want to convert this Purchase Requisition to Planned Order in APO and in the process clear the Purchase Requisitions in ECC and send planned orders to ECC. User will decide to convert this to Purchase Requisitions if and when he/she feels the need for it.

How do I accomplish this

What are the Pre-requisities other than int models and distribution definition for external procurement ?

Thanks

Amit

View Entire Topic
Former Member
0 Kudos

Dont you think planned orders and purchase requisitions without any supply source are the same? For simplicity sake lets assume the material is not a BOM. In which case they should be freely convertible between them. Like I planned to procure from someone a 1 month ahead. Though the supplier only needs a week's notice but somewhere in between I realize I have enough in house capacity during a planning run. I 'discover' this by changing source of supply manually in APO.

Does that sound like a reasonable business scenario?


Thanks

Amit

rupesh_brahmankar
Active Contributor

Hello,

Make sense, however think other way around, if I have a capacity available will produce in-house and if not then external.

So my planning output should be planned order which can be converted to in-house production or external purchase.

I think your scenario also fit in that.

Best Regards,

R.Brahmankar