on 2025 Dec 04 11:42 AM
Dear All,
Introduction:
We have 2 different locations, first one specific to deliver goods to customers but haven’t any stocks related to sales order line items, second location has stock and needs to transfer these goods to first location by system, then receipt stock in first location in this time stock it’s available to delivered to customer.
System process:
SO >> PR >> STO
Configurations steps:
SPRO --> Enterprise Structure --> Definition --> Sales and Distribution --> Define, copy, delete, check Sales organization --> Order Type.
Sales and Distribution --> Sales --> Sales Documents --> Sales Document Item --> Define Item Categories >>> Then enable check box Create PO automatic.
Sales and Distribution --> Sales --> Sales Documents --> Schedule Lines --> Define Schedule Line Categories.
PO Type --> as u have
Item Category --> 0
Account Assignment Category --> D
Then enable check box for Purchase requisition with delivery scheduling.
Item categories > MRP Type > Requirement type.
Go through MIGO > Transfer posting > Other > MVT 411 E
Insert sales order no, from & destination’s plant (second plant) in this time after post, the stock moved from special stock in sales order to unrestricted.
Regards.
Request clarification before answering.
Hi,
My suggestion is to use only STO without using the sales order.
The ATP control should be performed at the storage location and not plant levels.
You might also consider activating a dedicated MRP area to manage the transfer request.
Or activate the Badi MD_EXT_SUP (if available).
I hope this helps.
G
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 17 | |
| 16 | |
| 6 | |
| 3 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.