Hello,
That means there is no capacity available in that period non-working time. Check factory calendar assign to your resource also check if any downtime mainatined in resource master.
n the detailed scheduling planning board, working times are shown in white, regular non-working times (such as breaks and weekends) in gray, and downtimes (due to machine shutdowns, for example) in dark gray.
Refer useful SAP help document on it,
Scheduling in Non-Working Times - Detailed Scheduling Topics - SAP Library
Best Regards,
R.BRahmankar