Closing PO in SNC when GR is complete in ECC

Former Member
0 Likes
210

Hi,

We are having an issue triggering the POD output from ECC to SNC when the GR is completely done for a PO line item in ECC.

We are doing MIGO w.r.t IBD and after the PO gets updated for the "DEL COMPL" indicator but the PO output is not triggered from ECC to close the PO in SNC.

Has anyone faced the same issue?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Likes

Hi,

I had the same problem.

To solve it you can either:

Go to VL32n and manually add an output.

Extras --> Delivery Output.

Or,

add a condition record in MN24.

Best regards,

Duarte

Answers (1)

Answers (1)

Former Member
0 Likes

Hi,

Have you tried using the PROACT report to update GR status to SNC?

Secondly, refer to the below thread.

regards,

mahesh.