on ‎2025 Apr 03 7:17 PM
Hi Team,
We have few component quantity which are no longer required to be consumed against an order but in "Stage for Production" app these components are still showing as these needs to be staged because the PMR is exisitng. Can we get rid of these PMR"s which are no longer required to stage
example: For an order "O1", we need 100 EA of component "A". But we have completed the order by just staging and consuming 98 EA"s of "A". Now the order O1 is finally confirmed but in stage for produciton app, we still see 2 EA needs to be staged which is creating a confusion to the operators.
Can we clear the record for 2 EA from "Stage for Production" app ?
I know that it will be cleared if we change the quantity of component "A" in "O1" to 98 but this is not so feasible as we need to change for each order and we do TECO at the end of the month. We use cross- order staging.
Thanks
Vamsi Krishna
Request clarification before answering.
Well, the TECO mechanism the SAP standard for this purpose.
If you want to filter the relevant PMR items by other attributes you should think about implementing the BAdI /SCWM/EX_MFG_STAGE_INFO. The fallback class of this BAdI is the SAP standard algorithm for the staging proposals. The fallback class is not final, so you can easily adjust parts of it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 12 | |
| 7 | |
| 4 | |
| 3 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.