changing outbound delivery quantity in SAP EWM does not change outbound delivery quantity in SAP ERP

former_member709111
Discoverer
0 Likes
1,587

I have changed outbound delivery quantity with process code in SAP EWM. Also status of picking/packing and GI is completed.

but quantity changes are not reflected in SAP ERP outbound delivery. What could be the reason?

Regards

Gauri

Accepted Solutions (0)

Answers (1)

Answers (1)

Daniil
Active Contributor
0 Likes

HI Gauri, if you reduced quantity you maybe have to run /SCWM/R_PDO_COMPLETE report (should be planned as job). Or you can create Outbound delivery from /scwm/prdo transaction.