Hi experts,

How can I change the day of the week for the end date of purchase requisitions that the optimizer creates? Today the end date of the purchase requisition is on monday, I would like to change for the end of the week.

Thanks,

Accepted Solutions (0)

Answers (1)

Answers (1)

AyanBishnu
Active Contributor
0 Kudos

Hello jpns

In APO in the in LOCPROD View thier is a field called periodic factor in the lot size tab. maintain a value of 1 in that field. by putting value to 1 optimizer creates order at the end of the week. But I know for sure it works for planned orders if you dont have periodic factor in the PPM or PDS and i thik the same works for Preqs but you please recheck it using the help option against that field.