Hello

Yes, but if you are using SAP S/4HANA I strongly consider you to use the new Fiori Apps, because CM25 is part of the compatibility scope.

Details about those apps can be found in SAP Help:

https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/21aead0c98bd4755abdacd91c99e3393/96592cfe7187429c9a6...

Regards,
Caetano

RaghavanKathamuthu
Contributor
0 Kudos

Hi Caetano,

In planned orders there are no operation details.

How come the capacity palnning will happen.

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

You need to run MRP with detailed scheduling to see operation details. Also, make sure that there is a valid production version and routing for your planned order.

Answers (1)

Answers (1)

jduppalapati
Participant

Hi,

As it is in S4 HANA, Run it with detailed scheduling. With right master data routing and production version.