Capacity leveling for palnned orders

RaghavanKathamuthu
Active Contributor
View Entire Topic
Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Yes, but if you are using SAP S/4HANA I strongly consider you to use the new Fiori Apps, because CM25 is part of the compatibility scope.

Details about those apps can be found in SAP Help:

https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/21aead0c98bd4755abdacd91c99e3393/96592cfe7187429c9a6...

Regards,
Caetano

RaghavanKathamuthu
Active Contributor
0 Kudos

Hi Caetano,

In planned orders there are no operation details.

How come the capacity palnning will happen.

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

You need to run MRP with detailed scheduling to see operation details. Also, make sure that there is a valid production version and routing for your planned order.