on 2016 Aug 11 8:48 AM
Request clarification before answering.
Hello,
In ECC work center check the APO resource tab that External Capacity is aactive
and CFC9 check the setting for Use Ext. Capacity should be set to A when you want to transfer capacity to APO.
Refer consulting note 674838 - Resource transfer from APO Release 4.0
Best Regards,
R.Brahmankar