I am creating the Planning scope in VEMP_MAINTAIN. But got the below issue. Any idea?
Request clarification before answering.
BOM with engineering usage can only be used to create planning scenarios. So Engineering BOM usage E needs to be configured accordingly. The BOM should be created with this usage E
SIMG - Production - Basic Data - Bill of Material - General Data - BOM Usage - Define BOM Usages
SIMG - Production - Basic Data - Bill of Material - General Data - BOM Usage - Define Default Values for the Item Status
SIMG - Production - Basic Data - Bill of Material - General Data - BOM Usage - Define Copy Default for Item Status