Hi OBP experts,

In the Planning area 7F(OBP) we have Planning levels in Days, what if we make it to a Month only? Will there be any inconsistencies in the result from the Heuristics or Optimizer point?

Thanks,

Rahul

Accepted Solutions (1)

Accepted Solutions (1)

former_member654033
Contributor
0 Likes

Hi Rahul,

OBP Optimizer plans only at daily level (Telescopic planning is on IBP Roadmap for end of this year). Even if you create KF at month level, optimizer will still consider them at day level only (1st day of the week / 1st day of the month etc)

OBP Heuristic can plan at week/month level, I think you can setup periodicity at "settings for order based planning app"

Thanks

Girish

rahul_kumar124
Explorer
0 Likes

Thanks Girish, rightly pointed.

So you mean there will be no functionality impact in the case of Finite Heuristics, the idea is to save/create records at month level(moving planning level root of Day -> Month) so that OBP won't face performance issues due to processing more records.

Thanks,

Rahul

former_member654033
Contributor
0 Likes

yes, that is my understanding.