‎2020 Jan 11 12:07 AM - edited ‎2024 Feb 03 5:22 PM
I have one work order with several operations. Each operation will be done on different weeks. Is there a way to assign each operation its own revision, so that it can be scheduled at the appropriate time?
Request clarification before answering.
Thank you very much
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Not in standard SAP Chris..
You could add the revision to the operation "user-fields" (oreration Enhancement sub-tab). But thats just static data..
You'd then need a development to schedule the individual operations.
Note: you'll get a better response if you tag your posts with: PLM Enterprise Asset Management (EAM)/Plant Maintenance (PM)
.
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 17 | |
| 16 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.