on 2022 Jul 21 10:29 AM
Hi
Has anyone out here implemented or explored campaign planning within SAP IBP?
I have done so by fixing production to zero for certain production lines and then using the the adjusted key figures to manipulate the system to produce as per my requirement.
Have you a different approach that you can share?
Regards,
Mohammad
Request clarification before answering.