Hi guys,
Please share if it is possible in SAP IBP to branch a process chain depending on a logical condition like a weekday of execution or positive/negative result of the previous step. I use an application job template to make chains, but it enables to use of only one sequence of steps.
Request clarification before answering.
Hi Dimitrii,
You need to consider 3rd party job scheduling tool to achieve your IBP job scheduling requirement. It can trigger IBP application Jobs based on dependency setup in scheduling tool.
At present, IBP only offers sequential job template.
Thanks
Girish