on ‎2017 Jan 09 8:46 PM
Hi all
We have alternatives resources by classifying work centers in ECC. What we wont to acchive is to modify field DURVAR (activity duration variable) for each alternative resource.
We need diferents activity duration by resource.
Request clarification before answering.
Hello Carlos,
On APO side, Method CIF_IMPORT of BAdI /SAPAPO/CURTO_CREATE can be used to change variable and fixed duration for each mode.
On ECC side, you can try Method CHANGE_CIF_STRUCTURES of BAdI CUSLNTRTO_ADDIN.
Regards,
Tiago