Hello All,

We are facing issue while doing backward scheduling in SNP Capacity Leveling.

There is surplus hours available in W33 and there is shortage of hours in W34 so I select W33 and W34 and do the capacity leveling with backward scheduling.

System changes the hour for W32/W33 instead of W33/W34 which should noty happen.

It is working as expected when I choose Forward Scheduling.

Please help. Is there any setting issue ?

Regards,

Prabhat

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar
Active Contributor
0 Likes

Hello,

Please check if you have any holiday and no capacity on particular date of the week.

Also check if this SAP note valid for your release,

1974662 - Capacity leveling moves overload by one bucket only

Best Regards,

R.Brahmankar

Former Member
0 Likes

Thanks Brahmankar for your response.

This is happening for any 2 weeks I select - whether I select W33/W34 or W59/W60.

Also I noticed that this is happening only for one resource so not able to understand what settings might be causing this issue?

I checked by changing the calendar but issue still persists.

The note 1974662 - you referred is talking about other issue though it can be applied.

Regards,

Prabhat

rupesh_brahmankar
Active Contributor
0 Likes

Hello,

What do you mean by week W59/W60.? There are only 52 /53 weeks in a year.

So please check working/holidays in the factory calendar

Also cross check available capacity in that week and order lot size.

Best Regards,

R.Brahmankar