Greetings Everyone,

I am looking for a way to automatically have a group of associated activities' time updated when an activity time is changed to a different time slot. The idea behind this need is the following:

  • A service call will have a number of activities, for the sake of explanation, let's have 4 activities (Activity 1, Activity 2, Activity 3, Activity 4)
  • The activities follow a sequence of execution, meaning Activity 2 won't start unless Activity 1 is completed, same for Activity 3 and Activity 4.
  • In case Activity 2 has to be postponed by 30 minute, Activity 3 and Activity 4 will have to be postponed as well by 30 Minutes. (Please refer to the following screenshot)

Is there a way to configure this?

Thank you all in advance.

Best regards,

Khaled

Accepted Solutions (0)