Automatic splitting for Planned independent requirements

former_member4887
Participant
0 Likes
1,945

Dear SAP Experts,

We upload planned independent required manually using Transaction Code MD61 for next 6 months.

We have a requirement to split this monthly requirement equally into working days.I have tried doing it through MD62 & it works perfectly fine but when i try doing it via MD67 ( because i have a good no' of material for which i have to perform this activity & MD62 can only be used for individual material) it's not being divided equally.

The key that i use in period split for automatic splitting is as below :-

Please help me know what changes do i need to make to get the requirements equally divided among working days.

e.g Feb PIR = 200 & working days is 25. It should split 8 to every single working days.

I have tried searching similar thread but unable to understand how to fix this issue.

Regards,

Nida Anwaar

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar
Active Contributor
0 Likes

Hello,

Could you please check the calendar in SCAL where you have all working days in FEB?

System calculates a daily quantity and multiplies for the number of working days of the weeks

The demand is split according to the working days in the period.

Split a monthly requirement into weeks first by using Transaction MD67 and then then split these weeks into days.

Best Regards,

R.Brahmankar