on ‎2019 Jan 28 11:26 AM
Dear SAP Experts,
We upload planned independent required manually using Transaction Code MD61 for next 6 months.
We have a requirement to split this monthly requirement equally into working days.I have tried doing it through MD62 & it works perfectly fine but when i try doing it via MD67 ( because i have a good no' of material for which i have to perform this activity & MD62 can only be used for individual material) it's not being divided equally.
The key that i use in period split for automatic splitting is as below :-

Please help me know what changes do i need to make to get the requirements equally divided among working days.
e.g Feb PIR = 200 & working days is 25. It should split 8 to every single working days.
I have tried searching similar thread but unable to understand how to fix this issue.
Regards,
Nida Anwaar
Request clarification before answering.
Hello,
Could you please check the calendar in SCAL where you have all working days in FEB?
System calculates a daily quantity and multiplies for the number of working days of the weeks
The demand is split according to the working days in the period.
Split a monthly requirement into weeks first by using Transaction MD67 and then then split these weeks into days.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 17 | |
| 15 | |
| 3 | |
| 3 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.