cancel
Showing results for 
Search instead for 
Did you mean: 
Read only

Automatic offsetting between planned/process orders in APO

0 Likes
530

Hi All,

There is a business requirement to offset the planned orders generated by heuristic automatically(3 hours between). The orders will be using PDS quota (2 PDS) and accordingly they need to be created in a manner that there is this offset between them during bulk preparation phase. After this packing takes place on a single line which is a bottleneck resource.

Any idea how this can be achieved in standard?

Thanks in advance,

Ramesh

Accepted Solutions (0)

Answers (0)