Hi all,

Case: I am using single-order staging via PMR, therefore the stock delivered to PSA is assigned to a given production order. Stock at PSA is both HU-maned and batch-managed. I would like to consume entire stock that is linked with the PMR against the related production order. Is there an option to do it automatically once we the stock is staged? Or maybe I can set some background job that will trigger the goods issue?

Many thanks,
Marcin

Accepted Solutions (0)

Answers (2)

Answers (2)

Ajit_Routray
Active Contributor
0 Kudos

Hi marcin.cieslak

"Is there an option to do it automatically once we the stock is staged? "-> As per my knowledge, no unless you use back-flush ( its different scenario)

" Or maybe I can set some background job that will trigger the goods issue" -> Custom PPF (more flexible) would be the better solution in stead of background job...

Kind Regards,

Ajit

veereshkrs
Explorer
0 Kudos

Hi Marcin

Do you like to post the GI before Production order confirmation?

I hope GR of the finished product and GI of the components are posted at production order confirmation.

You can use synchronous goods receipt/goods issue in the production scheduling profile so that GI (261 mvt) is posted immediately without first creating a delivery/posting change.

Regards